Skip to main content

Civil & Infrastructure

Earthworks at North Technocity, Kulim

  • START DATE

    4th May 2021

  • PROJECT TITLE

    Proposed Earthworks And Associated Erosion And Sedimentation Control Inclusive Of Drainage Works And Detention Pond ("Works")

  • FINISH DATE

    3rd August 2022

  • CLIENT

    Northern Technocity Sdn Bhd 

  • DESCRIPTION OF PROJECTS
    • Site clearance works
    • Earthworks including removal of Unsuitable Materials (USM), cutting, excavation dan filling to the finish formation level
    • Drainage works including construction of concrete lined drain, drainage sump,inlet and outlet pipe / box culvert
    • Construction of detention pond
    • Slope protection by close turf
    • Road works
    • Environmental monitoring works