Proposed Bridge Crossing Sungai Pulai and Link Road from Pelabuhan Tanjung Pelepas to Tanjung Bin, Mukim Air Masin and Sungai Karang, Daerah Pontian and Mukim Pulai Daerah Johor Bahru
FINISH DATE
18 January 2023
CLIENT
SEAPORT WORLDWIDE SDN BHD
DESCRIPTION OF PROJECTS
2-lane dual carriageway with approximate length of 7.5km
Construction of raised embankment and elevated deck structure on low lying soft ground
Four (4) bridges crossing:-
Sungai Boh
Sungai Pulai
Sungai Perepat
KTMB railway line to PTP
Three (3) major junctions to be provided to tie into the existing roads and new developments.
To relocate / protect any existing services affected by the works
Provide street lighting along the roads and bridges.